Day 8 – April 10th

Today the Pinto Lake alum application project was completed ahead of schedule!  As planned, the exact dose of over 118,000 gallons of alum and buffer were applied in a precise, uniform…and most importantly…safe manner.  There is no greater measure of success than safety and Pinto marks HAB’s 55th project without a safety incident.  A special thanks to HAB’s Alum Transfer Specialist (Bernie Ruppert) for ensuring the our company Safety Plan is enforced and followed on all of our projects.  This level of detail and dedication is critical to successful applications.
This is the last of our daily postings, but check back periodically (or receive automatic notifications by entering your email address in the footer below) for additional project updates in the future.  Thanks for your interest and following our progress.  Don’t forget to check out HAB on Facebook, Twitter and Instagram too.  Finally, a big thanks to the community of Watsonville and the City of Watsonville staff for all of their support.  This support is also critical to successful projects.  We have definitely enjoyed our time here.  We are packing up and heading to Minneapolis for HAB’s next two projects…
DSC_4466
DSC_4800
DSC_4486
Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s