Day 7 – April 9th

HAB’s productivity has been high the last few days and we are slightly ahead of the remaining alum truck deliveries.  We applied 18,0000 gallons of alum and buffer to a 29 acre section of the lake before ending our workday at little early this afternoon.  This allowed us time to accept an invitation from a Pinto Lake resident to visit their home and gain a different perspective of the lake from the surrounding hills.  We also took the opportunity to enjoy a few competitive games of horseshoes and the beautiful weather and gorgeous view! It was much appreciated and demonstrates the deep support and interest in the Pinto Lake restoration project.  We have noticed this support all week and it really defines the importance of Pinto Lake to the Watsonville community.  It has been a fun experience to be a part of that!  We are on schedule to complete the application around noon tomorrow.

pinto horsesheos

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s