Day 1 – April 3rd

HAB spent day one of the project preparing equipment for the application.  This included assembly of the barge’s application boom, programing the barge’s computerized dosing system, launching the barge into the lake, setting up on-shore storage tanks and confirming the delivery plan for the alum and buffer.  The lake will remain open for approved uses during the application, but part of the parking lot is closed for use by the delivery trucks.